Projects
KLA Flue Stack
Newport
Location
KLA Manufacturing Facility, Newport
Client
CMB Engineering
Main Contractor
CMB Engineering
Engineer
Bingham Hall Partnership
Architect
Avante Architects
Tonnage
10t
Details
We completed the installation of the flue stack in mid 2024 following the installation of the adjacent gas bunker in the previous December.
The flue stack stands completely independent of the gas bunker to a total of 22m high.
The stack was assembled at ground level in two halves and lifted via a tandem lift by King Lifting, a man basket was then utilized to finalise the connection details.